| Contingency Funds | ||||||||
| Year 35 CDBG Budget Process | ||||||||
| Excess Public Service Funds | ||||||||
| $0.00 | ||||||||
| Excess Housing, Public Improvements, Economic Development Funds | ||||||||
| Harboursite Elderly | 2008 | $61,237.00 | Agency secured alternate HOME funds | |||||
| Passages Rehab | 2008 | $18,000.00 | Project Cancelled, selling building to RBS | |||||
| Passages | Rehab | 2007 | $205.00 | Project Complete - Excess Funds | ||||
| SUB-TOTAL - HOUSING, PI and ED | $79,442.00 | |||||||
| Contingency Totals | ||||||||
| Public Services | $ - | |||||||
| Hsg/EconDev/Public Improv. | $79,442.00 | |||||||
| Total | $ 79,442.00 | |||||||